Scrum – Provides you a good quick feedback on accuracy of estimates for tasks ..

One of the major dependencies for a successful project schedule is in terms of the accuracy of estimates versus the reality. In short, you want to measure the difference between the time estimate for a project (or a task inside the project), and the actual effort needed. For such a measurement, you would want to ensure that variables such as changes in feature specs or design between the estimate and the actual execution are eliminated; if your design changes between the initial estimate and when you sat down to do it, then it is very difficult to make such a measurement, or to learn something from such a measurement.
Consider the following example; a colleague of mine used to review the actual time spent on a task, and then compare it with the estimate for the same. He used to do this for multiple tasks, and where the variables (such as requirement changes, or design changes, etc) did not change too much during the time period, he would slowly start to learn which person tended to do the task earlier than the estimates given by the same person, and also the reverse. The next time he would ask these people for an estimate, he would accordingly make the relevant changes in the estimate he got, and then use the modified estimate for the final planning.
Scrum makes this review even more easier. In Scrum task tracking, the team is supposed to provide an update every day on what has been done, and which tasks will take up more time than initially planned. As a result, and especially because tasks tend to be defined in terms of hours and a few days rather than 5+ days, it becomes immediately clear as to which tasks are getting delayed. So, when you are using Scrum in your team, you will immediately start to see the variance between estimates and actual figures. Now, the development team may think that you are trying to find fault, but getting the estimates to be as close to actual figures is very important. This helps you better estimate the deliveries at the end of the Sprint, and prep the customer / product owner about what all is going to be delivered for which you want feedback. This also helps stakeholders get more confidence in the work done by the team.
Being able to see variance could also help you to figure out more research into why the estimates are getting varied; is it because the details provided by the Product Owner are not detailed enough to generate the right estimates, or is it because there are some design issues that cause more effort than people estimate. Make sure that this investigation is done.

The Elements of Scrum The One-Page Project Manager: Communicate and Manage Any Project With a Single Sheet of Paper
Practical Software Metrics for Project Management and Process Improvement

Leave a Reply

You can use these HTML tags

<a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <s> <strike> <strong>